sandvik.jpgLate in 2014 the technicians of an Egyptian Propane Dehydrogenation plant had to face the truth - several heat exchangers had failed unexpectedly and caused a production shut-down.

Fast action was needed. In close cooperation SANDVIK and the licensor developed a solution. The result - within just ten weeks, Sandvik had delivered 12 tons of super-duplex tubes (Sandvik SAF 2507) and proved the effectiveness of its express delivery program for duplex steels.

Besides major precautions when operating a plant unexpected material failures cannot be ruled out completely. In the case of the Egyptian plant, Sandvik says it was able to make a difference because of its extensive expertise in producing and testing seamless stainless steel tubes, its high delivery flexibility and its long-term and trusting relationship with the licensor.

t: +49 211 50 27 342

e: tubesales-de.smt@sandvik.com

w: www.sandvik.com

Click here for the full unedited version of the release as provided by the company

Sign up for the PWE newsletter

Latest issue

To view a digital copy of the latest issue of Plant & Works Engineering, click here.

View the past issue archive here.

To subscribe to the journal please click here.

Poll

"How is your manufacturing business preparing for a net Zero target?"






Twitter